www.ipsofactoJ.com/appeal/index.htm [2000] Part 4 Case 4 [CAM] |
|
COURT OF APPEAL, MALAYSIA |
|
Coram |
Yee Seng Plantations Sdn Bhd -
vs - Terengganu |
|
|
GOPAL SRI RAM JCA DENIS J.F. ONG JCA HAIDAR
MOHD NOOR JCA |
12
JUNE 2000 |
Judgment
Gopal Sri Ram, JCA
(delivering the judgment of the court)
THE
BACKGROUND
This
appeal has been brought against the order of the High Court at Kuala
Terengganu granting a declaration that certain paragraphs of a consent order
made in earlier proceedings between the appellant and the second, third and
fourth respondents are no longer binding on the respondents. To appreciate
the issues raised in this appeal, it is necessary to recite the factual
background against which this appeal rests.
The appellant was at all material times the sub-lessee of certain lands ("the said land") in Kerteh, in the State of Terengganu. The exact area of the said land is uncertain, as it has not been surveyed. But it is not in dispute that it is between 15,000 and 20,000 acres. In the years 1984 and 1986, the Government of the State of Terengganu acquired some 3,132 acres of the said land under eight notifications published in the Gazette. We will, for convenience refer to these 3,132 acres as "the acquired lands".
The
appellant objected to this acquisition and its objection was, in the usual
way, referred to the High Court under the provisions of the Land Acquisition
Act 1960. In the meantime the appellant took out an Originating Summons No
21 (24)-87-94 ("the first action") challenging the acquisition of
the acquired lands. The second, third and fourth respondents were cited as
defendants in the first action. The State Legal Adviser represented them.
Following negotiations between the appellant's solicitors and the State Legal Adviser, the first action was compromised. On November 17, 1991, counsel for the disputants appeared before the Judge at the High Court at Kuala Terengganu and recorded the agreement between them in the form of a consent order ("the said consent order"). It contains fourteen paragraphs. They read as follows:
|
(1) |
The Chief Minister, Terengganu, within the meaning of the Chief Minister (Incorporation) Enactment 1951 (hereinafter called the said Chief Minister) shall surrender or cause to be surrendered all the Concession land known as the Kerteh Concession, in the District of Kemaman, in the State of Terengganu (hereinafter referred to as the said Kerteh Concession) to the State Authority of Terengganu (hereinafter called the said State Authority), through the Director of Lands and Mines, Terengganu (hereinafter called the said Director of Lands and Mines); the said Kerteh Concession comprising of:
|
||||||
|
(2) |
The said Director of Lands and Mines; the Collector of Land Revenue, Kemaman, Terengganu (hereinafter called the said Collector of Land Revenue) and the said Chief Minister will assist the said Kerteh Concession land to be surveyed at the Plaintiff s own costs. |
||||||
|
(3) |
After the said survey of the said Kerteh Concession, the said Director of Lands and Mines; the said Collector of Land Revenue and the said Chief Minister shall then cause the said State Authority to alienate or re-alienate an area of not less than five thousand (5,000) acres of the land forming part of the said Kerteh Concession as delineated and coloured green on the plan annexed hereto to the Plaintiff abovenamed Yee Seng Plantations Sdn Bhd (hereinafter called the Plaintiff) by a Qualified title which shall be for the period of ninety nine (99) years at the premium not exceeding the sum of Ringgit Four hundred ($400.00) per acre and the said Qualified title to be replaced by a Final Title; |
||||||
|
(4) |
As the said Director of Lands and Mines; the said Collector of Land Revenue and the said Chief Minister are unable to alienate further acreage to the Plaintiff in the Kerteh Concession due to the same being: encumbered with the issuance of Temporary Occupation Licences, the said Director of Lands and Mines; the said Collector of Land Revenue and the said Chief Minister shall (subject to payment of dislocation costs to the Plaintiff as, hereinafter set out) cause the said State Authority to alienate, by a Qualified Title to be replaced by a Final Title, an area of a further five thousand (5,000) acres of the land at Ketengah as delineated and coloured blue on the plan annexed hereto after survey, to the Plaintiff for the period of sixty (60) years at the premium, not exceeding the sum of Ringgit Three hundred ($300.00) per acre. |
|
(5) |
The title or titles to the said lands to be alienated or re-alienated to the Plaintiff as set out in paragraphs (3) and (4) hereof shall be free of all encumbrances and restrictions of whatsoever nature except that, the same shall not be transferred or charged without the consent of the said Director of Lands and Mines and that the said lands can be used for such agricultural purposes as the Plaintiff abovenamed deems fit and all the lands alienated or to be re-alienated to the Plaintiff as aforesaid shall be absolutely vacant; |
||||
|
(6) |
On the alienation or re-alienation of said lands to the Plaintiff as aforesaid and on the issuance of the documents of title in respect thereof to the Plaintiff as aforesaid, the Plaintiff shall surrender the Kerteh Concession to the State Authority within 30 days from the delivery of the issued documents of titles as aforesaid to the Plaintiff, |
||||
|
(7) |
For the acquisition of the Kerteh Concession land pursuant to the aforesaid Land Acquisition References and other proceedings, after taking into consideration the alienation or re-alienation of the land at Kerteh as aforesaid, the alienation of the land at Ketengah as aforesaid and the dislocation costs as hereinafter set out, the said Director of Lands and Mines, the said Collector of Land Revenue and the said Chief Minister shall pay to the Plaintiff, the additional agreed sum of Ringgit Twelve million and five hundred thousand ($12,500,000.00). The Director of Lands and Mines, Terengganu, the Collector of Land Revenue, Kemaman, Terengganu and the Chief Minister, Terengganu shall pay or cause to be paid to the Plaintiff the said additional sum of $12,500,000.00 in the manner following, viz:
|
||||
|
(8) |
The said Director of Lands and Mines, the said Collector of Land Revenue and the said Chief Minister shall cause the deposits lodged Plaintiff in the Acquisition References to be refunded to the Plaintiff by the said Collector of Land Revenue or such other appropriate authority or authorities; |
|
(9) |
As the said Director of Lands and Mines, the said Collector of Land Revenue and the said Chief Minister are unable to alienate or re-alienate a further five thousand (5,000) acres of land in Kerteh to the Plaintiff, due to unavoidable circumstances understood by both parties, the said Director of Lands and Mines; the said Collector of Land Revenue and the said Chief Minister shall cause five thousand (5,000) acres of land in Ketengah to be alienated to the Plaintiff in lieu thereof as aforesaid, and the said Director of Lands and Mines; the said Collector of Land Revenue and the said Chief Minister shall further pay or cause to be paid to the Plaintiff, the further agreed sum of Ringgit three million ($3,000,000) as Dislocation Costs which said sum the said Director of Lands and Mines, the said Collector of Land Revenue and the said Chief Minister shall pay or cause to be paid to the Plaintiff as soon as practicable after the payment stipulated in Clause (7)(b) above but not later than 31st March 1993; |
|
(10) |
The Plaintiff shall be at liberty to appeal to the said Director of Lands and Mines, the said Collector of Land Revenue and the said Chief Minister or to the appropriate authority for a reduction in the premiums and the same shall be considered favourably by the appropriate authority or authorities; |
|
(11) |
All the lands to be re-alienated and alienated to the Plaintiff, as aforesaid, shall be subject to survey and shall be absolutely vacant; |
|
(12) |
In the event, the documents of title to the lands to be re-alienated and alienated to the Plaintiff are issued before the last payment of the monies is due for payment to the Plaintiff pursuant to paragraph 7(b) hereof, then the premiums payable shall be deducted from this payment. In the event the documents of title to the land to be re-alienated and alienated to the Plaintiff are issued after the last payment of the monies is due for payment to the Plaintiff pursuant to paragraph 7(b) hereof, then the premiums payable shall be paid by the Plaintiff on the issuance and delivery of the said documents of title to the Plaintiff, in which event the monies payable to the Plaintiff pursuant to paragraph 7(b) hereof shall be paid or caused to be paid by said Director of Lands and Mines, the said Collector of Land Revenue and the said Chief Minister on the date due for payment as therein ordered; |
|
(13) |
The Plaintiff shall not be at liberty to contend that the said Consent Order dated the 29th day of October 1982 made in Kuala Terengganu High Court Land Reference No I of 1979 is irregular or bad in law and shall not be at liberty to take any steps or any proceedings questioning the validity of the said Consent Order; |
|
(14) |
The Plaintiff shall not proceed further with the aforesaid Land References and shall withdraw or discontinue the same upon the finalisation of all the matters herein. |
It
is common ground (and the learned Judge accepted this) that following the
entry of this consent order steps were taken by the parties to the first
action to implement its terms. However, difficulties arose when the State
Authority, namely, the State Executive Council ("the Exco") of the
first respondent decided to reject the appellant's application for the
alienation of the Kerteh land referred to in the consent order. This
happened on July 23, 1996. The decision of the Exco was communicated to the
respondent by the Land Administrator in his letter dated February 3, 1997.
On May 29, 1997, the instant respondents commenced an action by an originating summons ("the second action"). In it they sought a declaration that they were not bound by the terms of the said consent order, in particular, but not limited to, paragraphs 3 to 14 thereof.
It
was the respondents' case in support of its summons that the second, third
and fourth respondents had fulfilled such of the terms of the said consent
order as lay within their power to do. In respect of the obligation to
secure the alienation of the Kerteh land, this was not something over which
they had any control. This is because of the provisions of the National Land
Code 1965 ("the Code") which vests the power to alienate land in
the sole discretion of the Exco. The decision of the Exco was a supervening
event over which the respondents had no control. As such the said consent
order, or so much of it as remained unperformed, was frustrated. The
respondents were therefore discharged from further performance of the
agreement embodied in the said consent order. So much for the respondents'
case.
The
appellant had, on July 30, 1997, taken out a motion in the first action to
enforce the terms of said consent order. At that point in time, the
appellant was unaware that the second action had been commenced. That is
because the respondents' summons in the second action was only served on the
appellant on August 3,1997. However, on the application of the learned State
Legal Adviser, the appellant's motion was adjourned pending the hearing and
disposal of the second action.
The
learned Judge who heard the second action agreed with the respondents'
arguments and granted the relief sought by them. The learned Judge declared
that the first respondent was not bound by the consent order dated November
17, 1991 made in the first action. He also declared that the consent order
had become frustrated in consequence of the decision of the Exco. He thus
absolved the second, third and fourth respondents from any liability for
non-compliance with the terms of the consent order. The appellants have
attacked these findings before us.
THE
ISSUES
Counsel for the appellant raised a number of issues during his argument. But in reality there are only three issues that are central to this appeal.
First, whether the first respondent had been impleaded as a party to the first action and was therefore bound by its terms.
Second, whether the consent order had become frustrated.
Third,
whether the respondents adopted the correct procedure. We will address
each of these issues in turn.
THE FIRST ISSUE
(Was the First Respondent bound by the consent order?)
It is a principle, fundamental to our system of jurisprudence, that only a party to proceedings may be bound by an order made therein. (See, Kheng Chwee Lian v Wong Tak Thong [1983] 2 MLJ 320.) As presently advised we find only two exceptions to this rule. Both are of limited application.
The first concerns injunctions which may be made binding upon the servants and agents of a party although such servants or agents are not themselves expressly made parties to the proceedings. (See, Brydges v Brydges & Wood (1909) P 187.)
The second exception is where a person who is interested in the proceedings is not a party but is "in reality fighting the suit, so to say, from behind the hedge" (per Viscount Radcliffe in lbeneweka v Egbuna [1964] 1 WLR 219.)
Thus, in Dewan Undangan Negeri Kelantan v Nordin Salleh [1992] 1 MLJ 697, Edgar Joseph Jr SCJ observed (at p 724):
|
As
for the other contention based upon the breach of the rule of
natural justice, to wit, that neither Samat nor Mahmud had
been made parties to the proceedings in the court below seeking
declaratory reliefs, and so had been denied the opportunity of being
heard, it is true that the grant of such reliefs would, and as
events turned out, did directly affect their position, and therefore
they should have been made parties to those proceedings. That,
however, is not conclusive of the issue before us. Those proceedings
had right from the start received considerable treatment in the
local press, and both Samat and Mahmud must have known
about them; yet they remained passive and did nothing; they made no
attempt to apply to be joined as defendants, which they certainly
could have done. A denial of the opportunity of being heard is a
wrong which is personal to the party aggrieved. If therefore such a
party does not complain, it is not the affair of others to complain. I find, therefore, that there is substance in the submission of counsel for the plaintiffs that the State Legislative Assembly of Kelantan is, in reality, as he put it, fighting the suit on behalf of Samat and Mahmud. In this context, I consider the following passage in the judgment of Viscount Radcliffe, speaking for the Privy Council in lbeneweka v Egbuna at p 266 to be apt:
Having regard to the very exceptional circumstances to which I have directed attention, I consider that the learned Judge was not prevented from making the declarations prayed for, in the exercise of his discretion notwithstanding the fact that two of the persons interested in the subject matter of the declarations were not before the court. |
The appellant has argued that the first respondent was indeed a party to the first action and was therefore bound by the terms of the consent order. In support of this submission, the appellant relies on the provisions of s 16(2) and (3) of the Code. Those provisions read as follows:
|
16. |
(2) |
Any action, suit or other proceeding relating to land in which it is sought to establish any liability on the part of the State Authority shall be brought against the State Director in the name of his office. |
|
(3) |
In any action, suit or other proceeding to which this section applies, the State Director may appear personally, or may be represented by any advocate and solicitor, any Federal Counsel, the State's Legal Adviser or any Land Administrator or other officer appointed under sub-section (1) of section 12. |
It
is manifestly clear from the plain language of the second subsection to s 16
that the State Authority is to be impleaded in a suit or other proceeding by
citing the State Director as a party. And, "State Director"
according to s 5 of the Code "means the Director of Lands and Mines for
the State appointed under s 12 and includes a Deputy Director of Lands and
Mines appointed thereunder."
It is not in dispute that the second respondent, the State Director, was a defendant in the first action. He was the first defendant. The State Authority was, therefore, a party to the first action by virtue of s 16(2) of the Code. Further, the State Legal Adviser represented the defendants in the first action. There is no suggestion anywhere in the affidavits delivered by the instant respondents in the second action that the learned State Legal Adviser had no authority to agree to the terms set out in the consent order. It would be quite intolerable if in these circumstances the State Authority were permitted to assert a lack of authority on the part of those nominated by the Code to represent it in litigation.
Further, it is equally clear from well-established authority that a State Government is bound by the doctrine of res judicata. In this context it is sufficient to quote from the 2nd Edn of Professor Hogg's work "Liability of the Crown", p 191:
|
The
doctrine of res judicata is sometimes treated as a kind of
estoppel, namely, estoppel by record. The doctrine stipulates that a
judicial decision (unless reversed on appeal) is binding on the
parties to the litigation, so that the same issue may not be
re-litigated by the parties: once decided by a court of competent
jurisdiction, the issue is said to be res judicata. The
doctrine is obviously required in order to bring disputes to an end.
Indeed, litigation would have little point if the losing party,
without appealing, or after exhausting appeals, were free to ignore
the judgment and return to the courts again. The Crown is bound by res judicata. Any other conclusion would be fundamentally inconsistent with the Crown's subjection to legal proceedings in tort, contract and other heads of liability, which must surely imply that the Crown is bound by the outcomes. |
It
follows from what has been said thus far that the first issue must be
resolved in the appellant's favour.
THE SECOND ISSUE
(Was there frustration?)
The consent order in the first action embodied the agreement that was entered into between the parties to the first action. It was therefore a contract that had been made into a rule of the court so that the ordinary principles governing the law of contract would apply in its enforcement. See, Tong Lee Hwa v Chin Ah Kwi [1971] 2 MLJ 75. A fortiori, the question whether any of the parties to the agreement embodied in the consent order has been discharged from further performance. The law of frustration is contained in s 57(2) of the Contracts Act 1950 which reads:
|
A contract to do an act which, after the contract is made, becomes impossible, or by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful. |
The
section postulates two supervening events that frustrate a contract. The
first is an event that makes the contract impossible of performance: the
second is the event of supervening illegality.
In Ocean Tramp Tankers v V/O Sovfracht [1964] 1 All ER 161 (CA), Lord Denning MR explained the operation of the doctrine. He said (at p 166):
|
It
has frequently been said that the doctrine of frustration only
applies when the new situation is 'unforeseen' or 'unexpected' or
'uncontemplated', as if that were an essential feature. But it is
not so. It is not so much that it is 'unexpected', but rather that
the parties have made no provision for it in their contract. The
point about it, however, is that: If the parties did not foresee
anything of the kind happening, you can readily infer that they have
made no provision for it. Whereas, if they did foresee it, you would
expect them to make provision for it. But cases have occurred where
the parties have foreseen the danger ahead, and yet made no
provision for it in the contract. Such was the case in the Spanish
Civil War when a ship was let on charter to the Republican
Government. The purpose was to evacuate refugees. The parties
foresaw that she might be seized by the Nationalists. But they made
no provision for it in their contract. Yet, when she was seized,
the contract was frustrated: see WJ Tatem Ltd v Gamboa [1938]
3 All ER 13 5. So, here, the parties foresaw that the canal might
become impassable. It was the very thing that they feared. But they
made no provision for it. So the doctrine may still apply, if it be
a proper case for it. We are thus left with the simple test that a situation must arise which renders performance of the contract 'a thing radically different from that which was undertaken by the contract': see Davis Contractors Ltd v Fareham UDC [1956] 2 All ER 145 at p 160; [1956] AC 696 at p 729), per Lord Radcliffe. To see if the doctrine applies, you have first to construe the contract and see whether the parties have themselves provided for the situation that has arisen. If they have provided for it, the contract must govern. There is no frustration. If they have not provided for it, then you have to compare the new situation with the old situation for which they did provide. Then you must see how different it is. The fact that it has become more onerous or more expensive for one party than he thought is not sufficient to bring about a frustration. It must be more than merely more onerous or more expensive. It must be positively unjust to hold the parties bound. It is often difficult to draw the line. But it must be done, and it is for the courts to do it as a matter of law: see Tsakiroglou & Co Ltd v Noblee & Thord GmbH ([1961] 2 All ER 179 at pp 185-187, [1962] AC 93 at pp 116, 119, per Viscount Simonds and per Lord Reid. |
Now, it is well-settled that the doctrine of frustration has no room where there is fault on the part of the party pleading it. Another way of putting it is that self-induced frustration is no frustration. See, Yap Peng v Public Bank Bhd [1997] 4 AMR 3817. The Master of the Rolls dealt with the point in Ocean Tramp Tankers v V/O Sovfracht (ibid) as follows (at p 165):
|
The second question is whether the charterparty was frustrated by what took place. The arbitrator has held that it was not. The Judge has held that it was. Which is right? One thing that is obvious is that the charterers cannot rely on the fact that the Eugenia was trapped in the canal; for that was their own fault. They were in breach of the war clause in entering it. They cannot rely on a self- induced frustration; see Maritime National Fish Ltd v Ocean Trawlers Ltd [1935] AC 524. |
So
too here. The refusal of the Exco to alienate the lands in question was a
deliberate act of non-compliance of the consent order by a party to the
first action. It was not a supervening event at all. In these circumstances,
it is not open to the instant respondents to rely on the doctrine. The
doctrine of frustration has absolutely no application whatsoever to the fact
pattern that forms the core of this appeal.
The other point raised by the respondents in the same context may also be conveniently disposed of at this stage. It has to do with s 29 of the Government Proceedings Act 1956. The respondents relied on proviso (b) to that section in support of their case. We will reproduce the whole provision. It reads as follows:
|
29. |
(1) |
In any civil proceedings by or against the Government the court shall, subject to this Act, have power to make all such orders as it has power to make in proceedings between subjects, and otherwise to give such appropriate relief as the case may require: Provided that- |
|
|
(a) |
where in any proceedings against the Government any such relief is sought as might in proceedings between subjects be granted by way of injunction or specific performance, the court shall not grant an injunction or make an order for specific performance, but may in lieu thereof make an order declaratory of the rights of the parties; and |
||
|
(b) |
in any proceedings against the Government for the recovery of land or other property the court shall not make an order for the recovery of the land or the delivery of the property, but may in lieu thereof make an order declaring that the plaintiff is entitled as against the Government to the land or property or to the possession thereof. |
||
The
proviso is relevant to coercive proceedings to recover land from a
Government, be it Federal or that of a State, e.g., on the expiry of a
tenancy. It is designed to prevent a writ of possession issuing against the
Government in execution of a judgment for possession. It follows that the
short answer to the respondents' argument is that the second proviso has
nothing whatsoever to do with the facts of this case. There is no bar to the
Exco binding itself to alienate land to any person. This is precisely what
happened here. Once the agreement was entered into and formalised as a rule
of court, it vested in the appellant a legitimate expectation that the
promise made to it will be carried out.
The law governing the doctrine of legitimate expectation in public law must now be taken to have been authoritatively settled by the judgment of the Federal Court in Majlis Perbandaran Pulau Pinang v Sykt Bekerjasama Serbaguna Sg Gelugor dengan Tanggungan [1999] 3 AMR 3529. There, Edgar Joseph Jr FCJ said (at p 3602):
|
For our part, we prefer the view of Simon Brown LJ in Exparte Baker [1995] 1 All ER 73 and Sedley J in Exparte Hamble [1995] 2 All ER 714 as we find the reasoning there more persuasive. It is also a view which appears to be supported by de Smith, as the following extracts from his book. Judicial Review of Administrative Action (5th Edn), indicate (at paragraph 13-034):
|
It
follows as a matter of pure logic from what we have said thus far, that the
respondents' contention based on s 42 of the Code also falls by the wayside.
That section vests the power in the Exco to alienate land. That is precisely
what the Exco agreed to do in the first action. At the risk of repetition we
would say that the Exco's later change of heart is not a supervening event
that frustrated the consent order. It was a breach of an obligation
voluntarily undertaken and given effect to in the form of an order of the
court.
For
these reasons, we would resolve the second issue also in the appellant's
favour.
THE THIRD ISSUE
(Was the correct procedure employed?)
Counsel
for the respondents has, both in his oral and written argument, submitted
that the respondents had employed the wrong procedure.
The
argument here is that a declaration in the terms sought by the appellant
would result in there being two inconsistent decisions in the same matter.
The judgment of Abdoolcader J, (as he then was) in Sungai Wangi Estate v
Uni [1975] 1 MLJ 136 was cited in support of this argument. With
respect, we do not agree with this submission.
It must be remembered that the respondents' case in the court below was that the consent order had become void because it had been frustrated. It was also their case that the order had been made in breach of written law, namely s 42 of the Code and the second proviso to s 29 of the Government Proceedings Act 1956. Assuming they were correct in these arguments, the result would have been that the consent order was a nullity as having been entered in breach of written law. In such event, the respondents would have been entitled to a declaration to that effect. The point is sufficiently covered by the decision of the Federal Court in Badiaddin Mohd Mahidin v Arab Malaysian Finance Bhd [1998] 1 AMR 909. That was a case where the appellant had taken out an originating summons for declaratory relief to rid himself of an order made in contravention of written law. Mohd Azmi FCJ who delivered the principal judgment of the Court said (at p 925):
|
For my part, I must hasten to add that apart from breach of rules of natural justice, in any attempt to widen the door of the inherent and discretionary jurisdiction of the superior courts to set aside an order of court ex debito justitiae to a category of cases involving orders which contravened 'any written law', the contravention should be one which defies a substantive statutory prohibition so as to render the defective order null and void on ground of illegality or lack of jurisdiction. It should not for instance be applied to a defect in a final order which has contravened a procedural requirement of any written law. The discretion to invoke the inherent jurisdiction should also be exercised judicially in exceptional cases where the defect is of such a serious nature that there is a real need to set aside the defective order to enable the court to do justice. In all cases, the normal appeal procedure should be adopted to set aside a defective order, unless the aggrieved party could bring himself within the special exception. |
Accordingly,
the reliance on Sungai Wangi Estate v Uni (ibid) is misplaced.
In any event, this court in Syarikat Kenderaan Melayu Kelantan Bhd v
Transport Workers' Union [1995] 2 AMR 1601 overruled that case. It is
our earnest hope that we will not hear of it again.
Further,
we agree with the submission of the respondents that a consent order may be
set aside in a fresh action on the same grounds on which an agreement may be
set aside. If authority is required for this proposition, it is to be found
in the decision of the Federal Court in Khaw Poh Chuan v Ng Gaik Peng [1996]
1 AMR 1057. However, whether an action to impeach a consent judgment in a
former action will succeed must depend upon the facts of the particular
case. And, as we have already said, the respondents in the present instance
have not made out a case to impeach the judgment in the first action.
MISCELLANEOUS
POINTS
The
appellant has raised several other arguments including an argument that the
respondents had acted inequitably in pursuing the second action when the
appellant had acted to its detriment in reliance of the consent order. Our
attention was drawn to the several acts done by the appellant upon the faith
of the consent order in the first action. We do not propose to discuss them
here. Neither do we propose to discuss the authorities we were regaled with
on the point. That is not to say that the points raised by the appellant
lack merit. But by reason of the route we have taken, we find it unnecessary
to deal with the other points raised by the appellant.
CONCLUSION
For
the reasons already given, the appeal succeeds. The declarations granted by
the learned Judge in the second actions are set aside. The respondents'
summons in the second action is dismissed. For completeness, the appellant's
motion in the first action is restored to file with a direction that it be
fixed for hearing. The appellant will have the costs of the appeal and those
incurred in the court below. The costs in this court include the costs of
the appellant's motion to add new grounds of appeal. The deposit shall be
refunded to the appellant.
Cases
Ocean Tramp Tankers v V/O Sovfracht [1964] 1 All ER 161 (CA); Syarikat Kenderaan
Melayu Kelantan Bhd v Transport Workers' Union [1995] 2 AMR 1601; Badiaddin Mohd Mahidin v Arab Malaysian Finance Bhd [1998] 1 AMR 909; Brydges v
Brydges & Wood (1909) P 187; Yap Peng v Public Bank Bhd [1997] 4 AMR 3817;
Dewan Undangan Negeri Kelantan v Nordin Salleh [1992] 1 MLJ 697; lbeneweka v
Egbuna [1964] 1 WLR 219; Khaw Poh Chuan v Ng Gaik Peng [1996] 1 AMR 1057; Kheng
Chwee Lian v Wong Tak Thong [1983] 2 MLJ 320; Majlis Perbandaran Pulau Pinang v
Sykt Bekerjasama Serbaguna Sg Gelugor dgn Tanggungan [1999] 3 AMR 3529; Tong Lee
Hwa v Chin Ah Kwi [1971] 2 MLJ 75; Sungai Wangi Estate v Uni [1975] 1 MLJ 136.
Legislations
Contracts
Act 1950: s.57(2)
Government
Proceedings Act 1956: s.29(1)(b)
Land
Acquisition Act 1960
National
Land Code 1965: s.5, s.12, s.16(2), (3), s.42
Authors
and other references
Hogg,
Liability of the Crown, 2nd Edn
Representations
RR
Sethu, S Kanawangi and Mokhtar Ngah (Mokhtar Ngah & Co) for Appellant
Adbul
Karim Abdul Rahman and Wan Farid Wan Salleh (Terengganu State Legal Advisor) for
Respondent.
Notes:-
This decision is also reported at [2000] 3 AMR 3209
|
|
all rights reserved taiking.thing pte ltd |
||