|
www.ipsofactoJ.com/appeal/index.htm [2004] Part 4 Case 7 [CAM] |
|
COURT OF APPEAL, MALAYSIA |
|
Judgment
Gopal Sri Ram, JCA
(delivering the judgment of the court)
This is an uncomplicated case. Its facts have been set out and discussed at length in the judgment of the High Court reported at [1997] 1 LNS 455. For present purposes, a short summary suffices.
The appellant and respondent entered into two contemporaneous agreements. One was for the transfer of land. The other was an agreement to fell and extract timber. It is the appellant's argument that both agreements should be read together. In support of her submission on the point, Miss Maidzuara relied on the following passage in the judgment of Raja Azlan Shah J (as he then was) in Mohamed Isa v Abdul Karim [1970] 2 MLJ 165:
|
It is a settled rule of construction that where several documents forming part of one transaction are executed contemporaneously, all the documents must be read together as if they are one (see Manks v Whiteley [1912] 1 Ch 735. This principle was followed in ldris Mohamed v Ng Ah Siew [1935] MLJ 257, where Terrell J at p 261 said:
In the present case, the two said permits to mine referred to the same subject matter and were substantially in identical terms except that the second permit was to take effect only a year later, that is, after the first permit had expired. In the circumstances, the two permits to mine should be read together as forming one permit to mine for a period of two years. |
Under the second agreement — I will call it the "timber agreement" — the appellant was to apply for a timber licence. It did not do so. Neither did the respondent transfer the land under what I will call "the sale of land agreement". According to the appellant it had carried out its obligations under that agreement and was therefore entitled to call upon the respondent to effect a transfer in its favour. The respondent says that it is for the appellant to apply for the licence in the first place. And, since it admittedly did not do that, there is nothing for the respondent to perform. So, this case has to do with the order in which the promises of the respective parties are to be performed. That, it is the only issue in this case is common ground between the parties.
Now, the order of performance of obligations in a contract is governed by s 53 or the Contracts Act 1950 which provides:
|
53. |
Where the order in which reciprocal promises are to be performed is expressly fixed by the contract, they shall be performed in that order; and, where the order is not expressly fixed by the contract, they shall be performed in that order which the nature of the transaction requires. |
The section is ipsissima verba s 52 of the Indian Contract Act 1872. In the leading textbook on the subject, viz, Singhal & Subrahmanyan's Indian Contract Act, 4th edn at p 984 the commentary to s 52 reads:
|
Standing alone, however, the mere order of performances in time is not always decisive of the case. The promise to render the earlier performance is not conditional on tender of an agreed equivalent by the other party; but may be conditional on other factors even though it is not expressly so provided. For example, the promisor's duty to render the earlier performance is constructively conditional on the absence of a material increase in his risk of not getting the agreed exchange. He is privileged to withhold his performance, if the other party repudiates in advance, or if, for any reason, he becomes prospectively unable to render the agreed exchange, whether because of objective impossibility, or of insolvency, or other personal inability. So, if a seller promises to ship goods on a certain day, in return for the buyer's promise to pay for them after delivery, the seller's duty to ship is constructively conditional on the buyer's prospective ability to pay. If the seller can show that the buyer will not in fact be able to pay, he is privileged not to ship; this is true, inspite of the fact that shipment is to be first in time. |
In the present instance, the two agreements when read together do not expressly fix the order of performance of the parties' respective obligations. Accordingly, the nature of the transaction must be looked at to determine this.
Taking the two agreements together and reading them as a whole and in the context of what Lord Wilberforce in his speech in Prenn v Simmonds [1971] 3 All ER 237 described as "the objective aim of the transaction", it is clear that the appellant cannot possibly apply to the appropriate authority for the licence until it becomes the registered proprietor of the land in question. For, it is commonsense that a non-registered proprietor has no standing to apply for the kind of licence contemplated by the timber agreement. In my judgment, in a purely commercial transaction such as the one we have here, the correct approach is to interpret the agreements in a way that is consonant with business commonsense. As Lord Diplock said in Antaios Compania Naviera SA v Salen Rederierna AB [1985] AC 191 at p 201:
|
While deprecating the extension of the use of the expression "purposive construction" from the interpretation of statutes to the interpretation of private contracts, I agree with the passage I have cited from the arbitrators' award and I take this opportunity of restating that, if a detailed semantic and syntactical analysis of words in a commercial contract is going to lead to a conclusion that flouts business common sense, it must be made to yield to business common sense. |
Unfortunately, the High Court did not take this approach. It treated the two agreements as separate contracts and dealt only with the appellant's obligations under the timber agreement without having any regard to the sale of land agreement. Consequently it failed to have any sufficient regard to the order in which the parties were to perform their respective obligations. In my judgment there is therefore merit in the complaints directed at the High Court's judgment by learned counsel for the appellant.
It follows that the respondent was clearly in breach of its primary obligation to transfer the land to, the appellant. Therefore it was not in a position to call for the performance of the appellant's obligation under the timber agreement to apply for the licence. The present case, in my judgment, falls plumb within s 55 of the Contracts Act 1950. That section says:
|
When a contract consists of reciprocal promises, such that one of them cannot be performed, or that its performance cannot be claimed till the other has been performed, and the promisor of the promise last mentioned fails to perform it, the promisor cannot claim the performance of the reciprocal promise, and must make compensation to the other party to the contract for any loss which the other party may sustain by the non-performance of the contract. |
Section 55 is, of course of general application when it speaks of the promisor having to pay compensation to the promisee. But, whether compensation is sufficient in a given case depends on the subject matter of the contract. Here the subject matter is land. A breach of a contract relating to land is rebuttably presumed to be irremediable by monetary compensation (s 11(2) of the Specific Relief Act 1950; see also, Zaibun Sa Syed Ahmad v Loh Koon Moy [1982] 2 MLJ 92). Having regard to the evidence before the High Court I find no material going anywhere near to rebutting the presumption housed in s 11(2). Hence, the appropriate remedy in this case is specific performance.
For the reasons already given, I would allow this appeal and decree specific performance of the sale of land agreement. The respondent must, within one month from today execute and hand to the appellant's solicitors a registrable memorandum of transfer in the appellant's favour together with the issue document of title to the land in question. In the event of the respondent's default in doing so, the senior assistant registrar of the High Court in Kuala Lumpur shall execute such transfer and the respondent shall within seven days of such default, deposit the issue document of title to the land with the senior assistant registrar. The appellant must bear the stamp duty, the registration fee and all costs attendant upon such transfer. The parties shall be generally at liberty to apply to the High Court for the purpose of carrying this order into effect. The respondent must pay the costs of this appeal and those incurred in the court below.
One final point. During his submissions learned counsel for the respondent faintly suggested that it may not be possible for his client to effect a transfer of the land to the appellant. That of course is wholly irrelevant at this stage. In the ordinary way, it must perforce be looked into on an application made in that behalf by the appellant to the High Court at the appropriate stage. See, Sekemas Sdn Bhd v Lian Seng Co Sdn Bhd [1989] 2 MLJ 155; Loo Choo Teng v Cheok Suiee Lee [2000] 2 MLJ 257.
My learned brothers Mohd Ghazali Mohd Yusoff and Arifin Jaka, JJCA have seen this judgment in draft and have expressed their agreement with it.
Cases
Antaios Compania Naviera SA v Salon Rederierna AB [1985] AC 191, HL; Loo Choo Teng v Check Swee Lee [2000] 2 AMR 1529; [2000] 2 MLJ 257, CA; Mars Equity Sdn Bhd v Tis 'ATA' Ashar Sdn Bhd [1997] 1 LNS 455, HC; Mohamedisa v Abdul Karim [1970] 2 MLJ 165, HC; Prenn v Simmonds [1971] 3 All ER 237, HL; Sekemas Sdn Bhd v Lian Seng Co Sdn Bhd [1989] 2 MLJ 155, SC; Zaibun Sa Syed Ahmad v Loh Konn Moy [1982] 2 MLJ 92, PC
Legislations
Contracts Act 1950: s.53, s.55
Contract Act 1872 [India]: s.52
Specific Relief Act 1950: s.11
Authors and other references
Singhal & Subrahmanyan, Indian Contract Act, 4th edn
Representations
Maidzuara Mohammad & Barbara Wong (Logan Sabapathy & Co) for appellant
Tommy Thomas (Tommy Thomas) for respondent
Notes:-
This decision is also reported at [2005] 1 AMR 237
|
|
all rights reserved taiking.thing pte ltd |
||