www.ipsofactoJ.com/appeal/index.htm [2005] Part 4 Case 9 [CAM]    

 


COURT OF APPEAL, MALAYSIA

Coram

Central Spectrum (M) Sdn Bhd

- vs -

Sri Ringgit Holdings Sdn Bhd

GOPAL SRI RAM JCA

ABDUL KADIR SULAIMAN JCA

ABDUL AZIZ MOHAMAD JCA

17 JUNE 2005


Judgment

Gopal Sri Ram, JCA

  1. This is a simple case. It concerns the interpretation of an agreement entered into between the parties to this litigation. It also concerns the meaning of s 136 of the National Land Code 1965 ("the Code") on which the plaintiff (the respondent before us) relied to establish its case before the High Court. But first the facts.

  2. The first defendant (the appellant before us) is a developer of 5860 acres of land in Pulau Indah, Selangor. The plaintiff purchased a plot of land measuring 87,820 square feet in that development. It was vacant land meant for industrial use. But the first defendant did not covenant to construct any building on it. The sale and purchase agreement between the parties is dated June 13, 1995. The plaintiffs case is that the first defendant is under a contractual or alternatively under a statutory obligation to provide access to the subject property. It does not appear to be in dispute that there is access to the development from the public highway. Equally, it is not in dispute that the first defendant has constructed an internal main road within the development. But there is no road connecting the plaintiffs lot to the internal main road. The undisputed documentary evidence shows that there a large monsoon drain has been dug in front of the plaintiffs lot so that there is no actual physical access to it. The plaintiffs complaint is therefore that its property is landlocked without access. The learned judge of the High Court found the plaintiffs complaint to be justified. The first defendant has now appealed to us.

  3. If the plaintiff is to succeed at all in this case, it must be able to point either to a term in the sale and purchase agreement imposing a duty on the first defendant to build a road connecting its land to the internal main road or to a statutory provision imposing such a duty. Now, we have scrutinised the sale and purchase agreement, in particular clauses 7 and 8 as well as the third and fourth schedules which we do not intend to reproduce here as they are of no assistance whatsoever to the plaintiff. We have read the agreement as a whole, including the clauses relied on by the plaintiff, and we are unable to find any obligation imposed on the first defendant of the nature suggested by the plaintiff. The aforesaid clauses merely require the first defendant to construct the internal roads in the development. They do not in any way impose a further obligation on the first defendant to construct a road over the monsoon drain connecting the plaintiffs lot to the internal main road.

  4. That brings us to s 136 of the Code. The section merely says that the state director is not to approve any application for sub-division of alienated land unless certain conditions are satisfied. Among these is a condition that the proprietor of the land shall agree in his application for sub-division that he will provide the necessary means of access by making up a road to the designated standard. By its tenor the section directs the state director to ensure there shall be a satisfactory means of access from any sub-divisional portion to a road or other public transport system, such as a river or railway station. It will be seen at once that the section is of no assistance to the plaintiff despite its learned counsel's sustained reliance on it. It is an administrative provision regulating the terms on which sub-division should be granted. It does not impose a duty on the first defendant to build a small stretch of road connecting the plaintiffs land, across the monsoon drain, to the main internal road.

  5. In the present instance, the land marked for development has already been sub-divided into separate sub-divisional portions. Also, the first defendant has provided access from the public highway to the whole of the land. So there is nothing in the point taken by the plaintiffs counsel and we really think that he has addressed the wrong target. The upshot is that it is for the plaintiff at its own cost to build the limited access road onto its vacant land.

  6. For the reasons already given we came to the conclusion that the learned judge fell into error in finding for the plaintiff. The appeal was accordingly allowed and those orders made that are usually made consequent upon the success of an appeal.

  7. My learned brother Abdul Kadir Sulaiman, JCA has seen this judgment in draft and has expressed his agreement with it.

    Abdul Aziz Mohamad, JCA

  8. The problem of access to the respondents' plot is as set out in paragraph 2 of the grounds of judgment of my learned brother Gopal Sri Ram JCA. The respondents' case was that it was the duty of the appellants to construct a way spanning the drain and linking the internal main road to the respondents' plot so that there would be access to the plot. That road, whose width is 39 feet, runs within a road reserve whose width is 100 feet. I he drain, whose width is 7 metres, runs within a drain reserve whose width is 10 metres. So the access way that the respondents need would span part of the road reserve and the entire drain reserve and would be outside the respondents' plot.

  9. The respondents' plot is an industrial lot and is part of "the development", which according to recital D in the sale and purchase agreement was the development of the master land by the appellants "for housing, commercial, industrial and warehousing purposes". In selling the plot to the respondents the appellants undertook in clause 7.1 of the sale and purchase agreement to provide the "basic infrastructure" specified in the fourth schedule to the agreement. In the fourth schedule the basic infrastructure is stated as one "to be provided for the development". Among the items specified in the fourth schedule is "roads and roadside drains". The learned judge decided that the word "roads" included an access way to the respondents' plot.

  10. In the appeal the appellants gave three reasons for maintaining that they were not obliged by the sale and purchase agreement to construct a means of access to the respondents' plot. Firstly, the appellants said in paragraph 9 of their skeletal submission that the "bridge or access" was to be constructed by the respondents because there was no requirement in the sale and purchase agreement for them to construct a "bridge" to the respondents' plot. It was an argument that failed to address the specific question of the meaning of "roads" in the fourth schedule, that is whether "roads" included a bridge that would provide access to the respondents' plot. The appellants did not argue why the word "roads", as a matter of interpretation of the word, could not include such an access. I think that the appellants focused on a bridge as the required access because in the High Court, according to the notes of proceedings, the respondents had maintained that the appellants should have constructed a bridge as a form of access.

  11. On the other hand, neither did the respondents argue strenuously why "roads" would include a bridge to their plot. By way of submission from the angle of interpretation they merely said in their skeletal submission (p 17):

    Access being a path of way linking one piece of land with another would clearly fall under the definition of "road".

  12. In deciding the question I confined myself to the consideration that the respondents' case was that the access to their plot should be in the form of a bridge. I considered that "roads" in the fourth schedule was intended to refer to roads of the ordinary type such as are seen in development projects. If such a road had to cross a stream or large drain, the part that would provide the crossing could be in the form of a bridge, and I had no doubt that that part would be a part of the road that the appellants were obliged by the sale and purchase agreement to provide. The appellants could hardly be said to have provided a road for the development if they did not also provide for a crossing over the stream or drain because then the road would not serve its purpose as people and vehicles would not be able to use it. But an isolated bridge to the respondents' plot would be just a bridge and would not fall within the concept of the ordinary type of road and neither would it be a part of the main road constructed to make the road passable. It would be incongruous with the ordinary concept of a road. It would be just an isolated structure of, say, metal sheets or concrete slabs of about 10 metres long. The situation may be likened to that of any ordinary lot in a housing development. There will generally be a small drain running along the front of the property parallel to the road serving the property. To enable a vehicle to get across the drain from the road into the property, something is placed over or across the drain, such as concrete slabs or metal grating. Such a structure can hardly be called a road. Of course, the drain in front of the respondents' plot is not a small drain, but the principle remains the same. The construction bridging the drain would not be a road of the ordinary type that is contemplated by the fourth schedule to the sale and purchase agreement. If the appellants and the respondents had put their minds to it and had intended that the appellants should provide an access bridge to the respondents' plot, they would have used some express words and not have simply relied on the word "roads" to express their intention.

  13. That was the thinking that led me to conclude that a bridge to the respondents' plot would not fall within the term "roads" and that therefore the appellants were not obliged by the sale and purchase agreement to provide the bridge and their appeal should be allowed.

  14. Although it was on that reason that the appellants, in my view, succeeded in the appeal, I shall nevertheless deal with their other two reasons because I am not in agreement with them on those reasons and I feel that, for the possible benefit of the respondents, I ought to state my reasons for disagreeing.

  15. As to the second reason, the appellants, also in paragraph 9 of their skeletal submission, argued that the bridge or access was to be constructed by the respondents because the appellants did not know the type of bridge that would be suitable for the factory to be built by the respondents on their plot. That argument could not affect the question of interpretation whether the word "roads" could include an access bridge to the respondents' plot, because if it could, and the appellants were therefore bound to construct the bridge, it should not be difficult for them to ascertain the type of bridge that would meet the respondents' needs.

  16. The appellants' third reason was based on clause 7.4 of the sale and purchase agreement. That clause, among other things, provided that "All internal roads ... and any other infrastructure work within the plot" shall be constructed by the respondents. In paragraph (in) at p 3 of their supplementary outline of submission, the appellants said this:

    The learned judge erred in not noticing the distinction between Basic Infrastructure for the Development as stipulated in the Fourth Schedule which refers to the basic infrastructure bar the Master Land as per the definition given in the SPA in the Recital D ... for the phrase "Development" against the stipulation in Clause 7.4 "All internal roads, ...." which refers to private roads to and fro the Plot and within the Plot.

    The significant thing to notice from that paragraph is that, to the appellants, the "internal roads" that clause 7.4 required the respondents to construct referred also to "private roads to and from the plot". The appellants were impliedly saying that the means of access to the respondents' plot, being a private road and a road to and from the plot, would be an internal road which clause 7.4 required the respondents to construct. The appellants did not explain why they said that an access way, which obviously, as I said, would be outside the respondents' plot, would be an internal road.

  17. I may mention that the respondents also relied on clause 7.4 to argue that it was the obligation of the appellants to build the means of access. They argued that since clause 7.4 obliged them to construct only roads within their plot, the linking access, which would be outside their plot, must be provided by the appellants. That was an argument that ignored the need to construe the word "roads" in the fourth schedule. If the word did not include the access as in fact I found, the appellants were not bound to provide the access and unfortunately for the respondents, they would have themselves, with the necessary approvals, to build the access that they need even though clause 7.4 does not oblige them to do so.

  18. As to the respondents' reliance on s 136 of the National Land Code particularly s 136(1)(h), the reasons in paragraph 4 of my learned brother' judgment essentially coincide with my reasons for rejecting it.


Legislations

National Land Code 1965: s.136

Representations

S Ramachandran, Murad Ali and CM Loo (Abu Hassan & Associates) for appellants

KH Lim (Lee & Lim) for respondents

Notes:-

This decision is also reported at [2005] 4 AMR 613


all rights reserved

taiking.thing pte ltd