www.ipsofactoJ.com/highcourt/index.htm [2003] Part 4 Case 13 [HCM]    

 


HIGH COURT OF MALAYA

Coram

ESPL (M) Sdn Bhd

- vs -

Harbert International Est Sdn Bhd

AZMEL MAAMOR J

29 MAY 2003


Judgment

Azmel Maamor J

BACKGROUND

  1. On August 2, 2002 the plaintiff had obtained, byway of an ex pane application (Encl. 6) a Norwich Pharmacal order and an Anton Pillar order against the defendant (the said orders). The said orders were immediately served on the defendant and executed. As such, action was taken by the defendant to apply to have the said orders set aside. It was originally fixed for hearing on August 12, 2002. On a request by the plaintiff to be given time to reply to the defendant's affidavit the hearing of the defendant's application was postponed to August 20, 2002. At this new date of hearing the counsel for the plaintiff complained to the court that the defendant had committed breach of the said orders and intended to take committal proceedings against the defendant and at the same (sic) applied for another postponement of this application. The learned judge allowed the postponement. In the meantime, the period of 21 days of the said orders had passed by.

  2. Before the defendant's application for setting aside the said orders could be heard 2 other applications were filed by the plaintiff. 

  3. In the light of the application for a committal proceedings the matter was referred to the managing judge of the civil division, YA Dato' James Foong. After giving his consideration, the learned judge directed that all the 3 applications be heard before me.

  4. At the time when the case was first fixed for hearing before me, on November 15, 2002, I requested counsel for both parties to give their views as to which particular application should be heard first. After having considered their arguments I decided to hear Encl. 16 first, i.e. the defendant's application to set aside the said orders. My reasons in arriving at this decision were as follows.

  5. Once it has been determined that the said orders have been properly and legally granted, then only it would be proper and just to proceed with the application for committal proceedings against the defendant. Based on such reasoning I decided to begin by hearing the defendant's application seeking to set aside the said orders under Encl. 16.

  6. However, in the course of my conducting the hearing of Encl. 16, it was decided at a meeting of the judges of the civil division, that the hearing of all matters in respect of this case be re-conducted by the original hearing judge, YA Dato' Abdul Malik Ishak. As such the file in respect of this case was transferred back to the learned judge for his further action. YA Dato' Abdul Malik, in his consideration, decided to hear Encl. 33 first and held Encl. 16 in abeyance. The defendant, being dissatisfied with that ruling of the learned judge lodged an appeal to the Court of Appeal. The matter was immediately heard. The ruling given by the Court of Appeal was that Encl. 16 should be immediately heard. As a result of that decision of the Court of Appeal I was directed by the managing judge of the civil division to continue with the hearing of Encl. 16 which I had previously part-heard. It was in the light of such circumstances that I proceeded to continue to hear the application under Encl. 16.

    BRIEF FACTS

  7. I shall now state briefly the facts of the case especially regarding the relationship between the plaintiff and the defendant. The Kuala Lumpur City Centre Project (KLCC Project) was owned by a company called Amalan Kreatif Sdn Bhd (the employer). The employer appointed a joint-venture of 4 companies calling themselves under the name Henz Construction (Henz) as the main contractor to develop and construct the said KLCC Project. The four companies that formed the joint venture (Henz) were:-

    1. Harbert-international Est Sdn Bhd (the defendant);

    2. Espirit Corporation Sdn Bhd (Espirit);

    3. Nam Fatt Bhd (Nam Fatt); and

    4. Zaq Construction Sdn Bhd (Zaq).

    (It would appear from the above that the name "Henz" had been formed by joining the first alphabets of the names of the 4 joint venture companies).

  8. As can be clearly seen, the defendant is one of the 4 partners of Henz, the main contractor.

  9. As the main contractor, Henz appointed various sub-contractors to deal with various parts of the works for the said KLCC Project. One of the Sub-Contractors appointed by Henz was Radio and General Engineering Sdn Bhd (R&G) to be responsible for carrying out the Electrical and Mechanical works. R&G decided to do the electrical works itself. As for the mechanical works, R&G had sub-sub-contracted such works originally to Econolev Singapore Pte Ltd (Econolev). Subsequently, the mechanical works were novated from Econolev to ESPL (M) Sdn Bhd (the plaintiff in this case).

  10. Technically R&G was the sub-contractor of Henz responsible to the main contractor for the electrical and mechanical works. And the plaintiff is the sub-sub-contractor of R&G responsible for doing the mechanical works. In an arrangement between R&G and the plaintiff it was agreed that both of them would open a bank account which was to be operated jointly by R&G and the plaintiff. It was also agreed that all monies and payments received from the main contractor in respect of the electrical and mechanical works would be deposited in the said bank account.

  11. The cause of complaint by the plaintiff against R&G arose from the fact that the plaintiff had not been fully paid for the mechanical works it had carried out in respect of the KLCC Project. The plaintiff also alleged that R&G without the consent of the plaintiff had unilaterally opened another bank account and had asked the main contractor, Henz to remit all payments in respect of electrical and mechanical works to the new bank account instead of to the agreed joint bank account. Arising from such complaint the plaintiff had brought civil action against R&G claiming for payments due to the plaintiff from R&G for the mechanical works done. 

  12. However R&G had also filed a counterclaim against the plaintiff claiming for defective works carried out by the plaintiff. (See Civil Suit No D8(D4) (S5)-22-620-1999). One of the several interlocutory applications made by the parties arising from the said suit was an application by the plaintiff to issue subpoena against the general manager of the defendant, Patrick Mitchell, seeking for an order that the defendant produce documents/final accounts relating to the electrical and mechanical works with a view to ascertain the exact amount of monies received by R&G from the main contractor in respect of the electrical and mechanical works. However, the application was rejected by the learned judge on March 14, 2002. An appeal against that decision had been filed by the plaintiff to the Court of Appeal and its decision is still pending.

  13. As explained above, the defendant was a partner of the joint-venture, Henz, who was appointed as the main contractor. There is no suit filed against the main contractor, Henz, nor against the defendant, except in respect of this matter. The basis of the plaintiff's claim against the defendant can be found in the plaintiff's generally endorsed writ of summons (Encl. 1); merely applying for two reliefs against the defendant, namely a Norwich Pharmacal order and an Anton Pillar order. There was no claim for damages for breach of any duty that had been committed by the defendant.

  14. From the facts and circumstances of this case, there was no evidence of any contractual relationship between the plaintiff and Henz or the defendant. The plaintiffs contractual relationship was only with R&G. However the plaintiff believed that the defendant as the leading partner of Henz was having in its possession most of the documents relating to the electrical and mechanical works concerning the KLCC project. The application for the Norwich Pharmacal order and the Anton Pillar order for a pre-action discovery was intended to uncover evidence relating to the identity of the wrongdoers who assisted/procured R&G in divesting monies for the electrical and mechanical works out of the joint bank account. The plaintiffs ex parte application for a Norwich Pharmacal order and an Anton Pillar order against the defendant was granted by the court. In the light of the above facts, the defendant applied to have the said orders set aside (Encl. 16).

  15. In applying to set aside the said Norwich Pharmacal order the defendant relied on the following grounds. 

  16. In respect of its application to set aside the Anton Pillar order the defendant gave the following grounds.

    The Anton Pillar would however be discharged as the respondents had not shown that there was a grave danger of the appellants destroying evidence for the purpose of the trial and there was no material before the court from which it could justifiably draw any inference that the appellants had the propensity to destroy or dissipate material evidence. There was, therefore, no ground for the respondent to even apply for the Anton Pillar order. After having carefully considered the submissions of counsels for both sides in the light of the whole facts and circumstances of this case I was of the view that there were strong merits in the arguments put forward by counsel for the defendant. On the facts that have been adduced and the arguments submitted before me, I was satisfied that the defendant comes within the category of a "mere witness".

  17. The act of the plaintiff in applying to the court for a subpoena of the general manager of the defendant in its action against R&G clearly indicates that the plaintiff had regarded the defendant as a mere witness. It would be a mala fide act on the part of the plaintiff to subsequently change its mind by no longer regarding the defendant as "a mere witness" through the application of the Norwich Pharmacal order. I also agreed with the defendant's counsel that the application of a Norwich Pharmacal order should have been made inter partes instead of ex parte. No valid reasons were given by the plaintiff for making the ex parte application. Based on those reasons the Norwich Pharmacal order should not have been granted.

  18. In respect of the Anton Pillar order I agreed fully with all the 3 grounds put forward by the counsel for the defendant that its application should not have been granted. And I do not wish to repeat them. Suffice it to state that the plaintiff had failed to show the existence of pre-requisite strong prima facie case against the defendant. In addition to that this Anton Pillar order should not in law be granted in aid of the Norwich Pharmacal order as had been granted in this case. I was also satisfied that there was no material whatsoever to show that there was grave danger of the defendant destroying or dissipating evidence for the purpose of the trial between the plaintiff and R&G. There was no material before the court which could infer that the defendant had the propensity to destroy or dissipate any material evidence in its possession.

  19. In the light of the whole circumstances of this case and for the reasons as I have stated above I arrived at the decision that the defendant's application to set aside the said orders be granted with costs.


Cases

Expanded Metal Manufacturing Pte Ltd v Expanded Metal Co Ltd [1995] 1 SLR 673. CA; First Malaysia Finance Bhd v Dato' Mohd Fathi Ahmad [1993] 2 MLJ 497; Golf Lynx v Golf Scene Pty Ltd (t/a Custom Golf Club Co) [1984] 59 ALR 343; Tat Sang Sdn Bhd v Saw & Co [2002] 4 AMR 4602; [2002] 7 CLJ 370; Teoh Peng Phe v Wan & Co [2001] 1 AMR 358; [2001] 5 MLJ 149

Legislations

Rules of the High Court 1980, Order 29 r 1(2B)

Representations

Cecil Abraham, G Rajasingam, Leonard Yeah & Brian Gumming (Tay & Partners) for plaintiff

Gideon Tan & Syamsuriatina Ishak (Gideon Tan Razali Zaini) for defendant

Notes:-

This decision is also reported at [2003] 6 AMR 122


all rights reserved

taiking.thing pte ltd