|
www.ipsofactoJ.com/international/index.htm [2000] Part 3 Case 11 [CFA] |
|
Judgment
Mr. Justice Ching
The appellant is a limited company which carries on the business of a designer. In 1990 it secured a contract with the Hong Kong Electricity Co. Ltd, to design, erect and later dismantle decorative lights on Hutchison House, the Furama Hotel and in Chater Garden. It had neither the expertise nor the plant or equipment to do the physical work which it contracted out to a sub-contractor, the firm of Easy Engineering Company, which engaged in that type of work. It was a partnership of two persons one of whom was the respondent who had successfully undergone a four year apprenticeship in and who was experienced in electrical work. The lights were successfully installed. The dismantling was carried out from a platform of an appliance called a mobile ladder scaffold. It had no ladder but it did have cross pieces three feet apart which were used by the workman to gain access to and egress from the platform. On 27 November 1990, while the respondent was climbing down in this way he fell and suffered very serious injuries.
In these circumstances the respondent issued proceedings against the appellant alleging common law negligence and a breach of regulation 38A(a) of the Construction Sites (Safety) Regulations, Cap. 59. The claim was dismissed at first instance. The respondent appealed against the findings on the breach of the regulation alone and was successful to the extent of 50%. We are therefore concerned only with the breach of the regulation which reads,
|
38A. |
General |
|
|
Without prejudice to the other provisions of this Part, the contractor responsible for any construction site shall ensure that - |
||
|
(a) |
there is, so far as is reasonably practical, suitable and sufficient safe access to and egress from every place on the site at which any person at any time works .... |
|
At trial it was found by the judge that the appellant came within the words 'contractor responsible for any construction site." Before us Mr. Lui Po Man, a director of the appellant who was given leave to appear and argue the appeal, said that at the time of the accident the appellant was not such a contractor. It is clear that the appellant gave notice to Easy Engineering that the dismantling was to take place between 5 and 9 November 1990, while the accident took place on the 27th of that month. He said that the appellant was not aware that Easy Engineering was working on the site on that day and that no representative of the appellant was then present. These assertions were neither pleaded nor investigated at trial. Whatever the merits of the argument may be this Court is quite unable to come to any decision upon it. We must therefore proceed on the basis that the appellant was in fact the contractor responsible for the site at the relevant time.
Throughout the proceedings in the courts below and before us the appellant was unfortunately not legally represented. Mr. Godfrey Lam of counsel kindly accepted an appointment as amicus curiae and we are grateful to him for the lucid arguments which he presented. It is apparent that the outcome of this appeal turns upon one of three points.
The first of these points is whether or not it is permissible to contract out of civil liability for breach of the regulation with a workman and, if so, whether the sub-contract in this case did so. The sub-contract contained a number of items under the heading 'Work description' of which item 7 reads,
|
please include in the works if scaffolding is needed. |
It must be said that a contractual duty to provide necessary scaffolding does not of itself relieve a party in the position of the appellant from its duty to ensure, so far as is reasonably practical, safe access to and egress from the workman's place of work. Item 14 then provides,
|
All safety rules based on Hong Kong Labour Department's labour safety regulations. |
It is difficult to find that the appellant intended to refer to regulations such as the one in question when it admitted that it had no knowledge of any of them. Even assuming that that was what was intended this item seems to provide simply that Easy Engineering was to comply with whatever regulations there were. It certainly does not provide that the appellant was not to be liable for any breach. In these circumstances the question of whether or not it is permissible to contract out for such a breach does not arise.
There was another document which appears to have been given by the appellant to Easy Engineering consisting of a number of notes (the Notes). The contents were treated by both courts below as being terms of the sub-contract and this was not disputed before us. In paragraph 6 under the heading 'Safety Measures' it is provided that,
|
For high level and outdoor work, all workers must have appropriate safety equipment and take safety measures. Those working at high level must wear safety belt and link all tools to avoid an accidental fall. It is the responsibility of the contractor to provide safety equipment, like safety scaffoldings, safety belt, and high level work warning sign. Otherwise the contractor will have to shoulder all consequences. The suspended box will cease operation when the black (storm) signal or higher signals are hoisted by the HK Royal Observatory. This is to ensure safety. |
It appears that the words in the sub-contract for 'safety scaffolding' were the same as those used in the Notes. In the former but not in the latter the translation was amended to read 'protection fan' which I understand mean cladding around the scaffold to protect from falling objects. There is no reason to suppose that the words should not be given the same translation in the Notes. However that may be, the purpose of the regulations is clearly to provide for the safety of workmen and the primary responsibility for this must rest with the contractor responsible for the site. On the assumption that there can be a contracting out, very clear words would be needed to exclude the contractor from civil liability for breach of any of the regulations. I do not find any such clear words in either the sub-contract or in the Notes providing for this. The 'Safety Measures' set out above are apt to provide that the sub-contractor is to provide safety equipment such as safety belts and high level work warning signs, and perhaps ladders, but that is not enough to absolve the contractor responsible for the site from liability for breach of the regulations.
I pass then to the second point which is what has been called the 'special defence'. It has been established by high authority that where an employer has used all due diligence to fulfil its statutory duties it may avoid civil liability where it is shown that the accident causing the injury was solely due to the breach of those duties by the workman himself. See Lord Reid in